Tape correction exercise: reduce two sloping spans to a horizontal baseline
Apply the tape calibration before reducing two unequal slopes, then test the result against the shortcut of using only the net rise.
On this page
Field observationsApply the length scaleResolve each slope on its ownExpose the tempting shortcutMarking notes and a field extensionA nominal 30 m tape measures 30.012 m under the conditions of this exercise. The tape is long. Does that make the corrected length of a measured line longer or shorter than the number written in the book? Decide the sign before calculating. Then determine whether the hill between the endpoints can be replaced with one straight slope.
Field observations
A, B and C lie on one straight line in plan. In profile, B sits above both neighboring endpoints. Two separate taped slope spans were observed end to end, with no plan-angle turn at B. The exercise assumes straight tensioned spans, identical calibration and field conditions, negligible sag, and elevation differences measured independently between the same tape endpoints. All quantities are in metres.
| Span | Tape indication along slope | Elevation change, end minus start |
|---|---|---|
| A to B | 30.000 | +3.200 |
| B to C | 24.000 | −1.800 |
Determine the corrected slope length of each span, the horizontal distance AC measured along the common plan line, and the total elevation change. Report the horizontal result to the nearest millimetre. Explain whether you could get the same result by adding the tape indications, correcting that single length, then using only the net elevation change.
Apply the length scale
Each nominal metre occupies 30.012 / 30.000 = 1.0004 actual metres under the stated conditions. Thus AB’s corrected slope length is 30.000 × 1.0004 = 30.012 m. BC’s corrected slope length is 24.000 × 1.0004 = 24.0096 m. The longer tape covers a greater actual distance for a given field indication. The positive correction follows from that physical interpretation.
Only the tape observations receive this calibration factor. The independent elevation differences did not come from this tape. Scaling them too would silently change the supplied data. If an actual survey determined heights from the same equipment, it would require a separate analysis of how the relevant observations were reduced.
Resolve each slope on its own
For a straight span with slope length S and elevation difference h between its endpoints, its horizontal component is the square root of S² − h². Apply that relationship to the two spans before adding them.
- AB projects to √(30.012² − 3.200²) = 29.840914 m.
- BC projects to √(24.0096² − 1.800²) = 23.942032 m.
- Their plan lengths sum to 53.782946 m, or 53.783 m to the nearest millimetre.
The total elevation change is +3.200 − 1.800 = +1.400 m. The minus sign on the second slope matters when accumulating elevation. Squaring its magnitude for the individual horizontal reduction removes the sign in that calculation. These two uses of the elevation difference answer different geometric questions.
Expose the tempting shortcut
The two corrected slope lengths add to 54.0216 m. Treating that value as the straight distance from A to C combines two inclined segments that bend at B. Using the net rise of 1.400 m with that broken-line length would yield about 54.003 m in plan. That exceeds the correct answer by approximately 0.221 m when the difference is evaluated using unrounded values.
An independent sketch explains the direction of the error. Walk uphill and then downhill. Your travelled slope distance includes both changes, but the endpoint rise remembers only their difference. The shortcut spreads a small constant gradient over the entire walk and removes the intervening crest from the model.
Marking notes and a field extension
Give credit for applying the tape factor to each recorded slope, retaining intermediate precision and checking that each horizontal component is shorter than its own slope. A student who reports the correct final elevation change but gives 54.0216 m as the plan distance has stopped one reduction too early.
For an extension, move B sideways so the two spans turn in plan. Their corrected horizontal lengths would then describe the traveled horizontal path. The straight-line distance AC would also require the included angle or endpoint coordinates. Ask which extra observation the field crew should record before accepting a distance called “baseline AC.”