Divide a cross section into cut and fill at the grade crossing
Plot four offset levels, interpolate the crossing with a flat formation and integrate separate cut and fill areas using trapezoids.
On this page
Plot the field sectionLocate the zero crossingCalculate the areas in square metresCheck the result and explain its limitsAt one station the ground sits above formation on the left and below it on the right. A single signed area hides how much material is on each side. This exercise asks for two separate cross-sectional areas. It also makes you locate the exact zero crossing between observed offsets before using the trapezoid rule.
Plot the field section
Offsets are measured perpendicular to the alignment in metres. Negative offsets are left when looking in the direction of increasing chainage. Ground is linear between the observed offsets and the proposed formation is horizontal at 102.00 m across the entire 12 m width.
| Offset (m) | Ground elevation (m) | Formation (m) |
|---|---|---|
| −6 | 102.80 | 102.00 |
| −2 | 102.40 | 102.00 |
| +2 | 101.60 | 102.00 |
| +6 | 101.00 | 102.00 |
Plot offset horizontally and elevation vertically. Subtract formation from ground at each observed offset. Use positive depth for cut and negative depth for fill, and write this convention on the sheet. The four signed depths should be +0.80, +0.40, −0.40 and −1.00 m. Mark the cut and fill portions with different hatching so they remain distinguishable on a black-and-white print.
Locate the zero crossing
From offset −2 to +2 the depth changes from +0.40 to −0.40 m over a width of 4 m. The zero occurs after a fraction 0.40/(0.40 + 0.40) of that width. Half of 4 m is 2 m, putting the crossing at offset zero. Add that interpolated point with depth zero to the working table. This makes every subinterval entirely cut or entirely fill.
If the two depths had been +0.10 and −0.70, the crossing would lie much closer to the left observation. Assuming the centerline is always where cut meets fill would fail on that section. What determines the crossing is the relative magnitude of the signed depths on either side.
Calculate the areas in square metres
Between −6 and −2 the cut area is width 4 × average depth (0.80 + 0.40)/2 = 2.40 m². Between −2 and zero it is 2 × (0.40 + 0)/2 = 0.40 m². Total cut is 2.80 m². The second strip is a triangle, which provides a quick visual check of the trapezoid calculation.
From zero to +2 the fill area magnitude is 2 × (0 + 0.40)/2 = 0.40 m². Between +2 and +6 it is 4 × (0.40 + 1.00)/2 = 2.80 m². Total fill is 3.20 m². The signed cut-minus-fill result is −0.40 m². That net number is useful as a consistency check but loses the individual quantities if reported alone.
Check the result and explain its limits
Integrate the original three signed strips without inserting the zero point. Their signed areas are +2.40, zero and −2.80 m², again yielding −0.40 m². The central strip has zero signed area because it contains equal triangles of opposite sign. A student reporting zero material in that strip has confused cancellation with absence.
Award marks for the offset convention, the signed-depth table, the interpolated zero offset and separately labeled cut and fill totals. Require square metres, because a single section has width and depth but no along-route length. To obtain a volume, survey or model additional sections and specify how their areas vary between chainages. These results also exclude side slopes beyond the stated offsets, stripping, shrinkage and material suitability. Including any of them would change the section definition and require more data.
For a final unit check, multiply both areas by a hypothetical one metre of uniform length and explain why that assumption would need field verification.